Nu på torsdag eftermiddag (30 juli) stänger vi verksamheten i Uppsala. På fredag fortsätter vi att plocka och packa delar på lagret inför flytten...
Lördag och söndag (1-2 augusti) flyttar vi!
Eng: The move to our new warehouse is now very close! This past weekend we where three/four guys sealing some of the warehouse concrete floors with "Lithurin".
On Thursday (July 30) we close the business in Uppsala. From friday we start preparing for the final move to Enköping. This upcoming Saturday and Sunday (August 1-2) we will do the final move - wish us luck... :)

Eng: There is now a pallet system in the 560 sqm sized high-rise warehouse. The highest level is 6 meter from the floor.


Eng: we bought this used old beat-up truck quite recently - we'll see if we keep it... It can at least lift the pallets 6+ meters up.

Eng: The cleaning of the concrete floors took all Saturday to do. This part is pretty much in the middle of the house. To the left you'll see the entrance to the automated elevator rack systems (they will be installed later this fall).

Eng: This part of the flooring is still to be treated with Lithurin at the warehouse. We'll fix it after we have moved in.

Eng: There is already quite a lot of standard shelf racks in the warehouse now. But within a week it will be slightly more stuff here... :)

Eng: The left part of the smoothened concrete floor is treated with Lithurin IIS and is almost dry so one can walk on it. The part in the middle is wet and being "massaged" and the right hand side is cleaned and primed with the Lithurin hardener. The top coat of Lithurin IIS should be kept wet and "massaged" for 20-30 minutes before let dry. Do note, we did 6-700 sqm of flooring like this... Twice in 7 hours...